Investment in construction of Vinh Yen city wastewater treatment plant phase II

08/04/2021

1. Investment place: Quat Luu Commune, Binh Xuyen District, Vinh Phuc Province.

2. Area: About 10,000m2.

3. Objectives: To improve urban people's living standards through appropriate technology of wastewater treatment to ensure water quality before being discharged into the environment according to current regulations.

4. Expected investment scale: 6,000M2/ day and night.

5. Total expected investment amount: VND 140 billion.

6. Capital source: State funding.

7. Expected investment form: Direct Investment.

8. Expected schedule: 2021-2022.

Source: Decision No. 820/QD-UBND dated April 06, 2021