The project on parallel road with Hanoi - Lao Cai railway (the North and the South), the section from Hop Thinh - Dao Tu road to National highway 2 (Viet Xuan commune, Vinh Tuong district)

21/11/2019

1. Investment objective: Connecting important roads in the province such as National Highway (NH) 2, TransAsia road, Hop Thinh - Dao Tu and Phu Hau bridge; forming a favorable transportation network, creating momentum to promote the local socio-economic development. Creating momentum for the local socio-economic development to catch up with the general development of other districts in the province, promoting the socio-economic development, attracting small and medium-sized enterprises, contributing to transform economic restructuring from agriculture to industry - service - trade. Traffic safety for the travel of people and vehicles when having to go through railways.

2. Investment scale: The total length of the route is about L = 8.4 km (including 4.4 km long of the North railway from the overpass of Hop Thinh - Dao Tu road to ring road IV and the Southern route 4, 0 Km from ring road IV to the intersection of NH2 with the road leading to Hac Tri bridge in Viet Xuan commune, Vinh Tuong district); Bbackground = 24,0m (in which: Bpavement = 1,5m, adjacent to the railway; Bsurface = 2 * 8,0m; Bpavement = 4,5m; BGPC = 2,0m). Structure of asphalt concrete pavement, vertical drainage items, horizontal drainage, bridges on roads, sidewalks, green trees, lighting, traffic safety systems, slip roads to intersections with the overpass of synchronous belt road IV.

3. Project group: Group B

4. Total investment of the project: VND 710,000 million.

5. Investment capital sources:

- From the provincial-level budget expenditure savings source from 2018 to 2019 is VND 50,000 million;

- From the source of the provincial budget surplus in 2018 transferred to 2019 is VND 50,000 million;

- From the capital source of medium-term public investment plan for the 2016-2020 period is VND 110,000 million;

- From the capital of public investment plan in the period of 2021 - 2025: VND 500,000 million.

6. Project location: Hop Thinh commune, Tam Duong district, communes of Yen Binh, Chan Hung, Nghia Hung, Yen Lap and Viet Xuan, Vinh Tuong district.

7. Implementation time and progress: 2019-2024.

 (According to the Resolution of the Vinh Phuc Provincial People's Council Session XVI,
13th session, adopted on October 23, 2019).