The Project on East-West axis road of Vinh Phuc urban area (The section from Tan Phong to Trung Nguyen)

21/11/2019

1. Investment objective: Gradually perfect the infrastructure system of Vinh Phuc urban framework according to the approved zoning plans of B1, B2 and B3. Promote urban development and service of the socio-economic development step by step.

2. Investment scale:

- The length of the route is about L = 7.16 km: The starting point intersects with Km3 + 200 Huong Canh - Tan Phong road; the end point intersects with Km2 + 400 Trung Nguyen - Ma Lo street.

- Scale of plain delta road level III: B platform = 12m; In which: B surface = 11m; B edge = 2x0.5m.

3. Project Group of: Group B, field of transportation.

4. Total investment of the project: VND 287,000 million.

5. Investment capital sources:

- From the source of increasing provincial budget revenues in 2016 to 2019: VND 38,000 million

- From the provincial budget saving and spending source in 2019: VND 92,000 million;

- From the capital of public investment plan in the period of 2021-2025 is VND 157,000 million

6. Project location: Binh Xuyen district, Yen Lac district, Vinh Phuc province.

7. Implementation time and progress: 2019-2023.

 (According to the Resolution of the Vinh Phuc People's Council Session XVI,
13th session, adopted on October 23, 2019).